
NORWALK, Conn. — Design plans for the Jefferson Elementary School renovation are on track to be complete by the end of June, with construction to begin early next year.
The Common Council Land Use and Building Management Committee got an update on Jefferson and other school projects Wednesday, focusing on Jefferson’s energy savings plans in response to pleas from activist Diane Lauricella. The new Norwalk High School project did not advance, in a move that was described as a technicality.
Jim Giuliano of Construction Solutions Group, the city’s project manager for new school construction, said he’s putting together grant applications for the Naramake Elementary School kitchen, Cranbury Elementary and Norwalk High School, and will be ready to submit them to the State by the June 30 deadline.
But the Committee tabled authorization of schematic drawings for Norwalk High School, and the authorization to submit a grant application for the project. Committee Chairman Thomas Livingston (D-District E) said there was no point, given that the legislature ended its session Wednesday.
Special legislation is needed for the promised 80 percent reimbursement for project, Lo explained. It was thought this would happen in April but due to the pandemic, it will likely take place in June or July.
“By not approving this tonight, doesn’t mean that we’re not going to apply for it,” Lo said. “I mean, all we’re saying is that we were delayed because of their schedule (getting) pushed over.”
The Cranbury project has a June 30 deadline, but the Norwalk High School project “is the last year’s money and then we need a special appropriation, a special legislation to get approval,” Lo said. “…The state’s going to delay this, so the submission date is going to be delayed for this project.”
“Hopefully, we’ll have more information at that point,” Livingston said. “I mean, it could be moot for all we know. If they have a special session and don’t approve it.”
There’s a placeholder for the project in the 2020-21 capital budget, Finance Committee Chairman Greg Burnett (D-At Large) said.
That makes sense because it will be submitted in 2020-21, not in the current fiscal year, Livingston said.
“We’re not saying we’re not going to approve it. It’s just at this point, it’s not timely,” Livingston said.
School updates
Work at Ponus Ridge Middle School has accelerated given that the building is empty and the project will be done a little ahead of schedule, Building and Facilities Manager Alan Lo said. But any savings are counter balanced by COVID-19 expenses, such as having medical staff present to check on the workers health before they enter the site. It’s also cleaned daily.
Numbers are not yet available, he said.
“We’re going to have to see how that plays out,” Giuliano said.
The Jefferson plan did not include windows along the side of the new gymnasium that’s planned for the upper level, an idea that was floated in early February.
Architects are striving to reduce the water leaving the site and have planned security enhancements, such as a “mantrap” off the entrance, two vestibules that allow pedestrians in or out. Security will have an office adjacent to the entryway.
Livingston read a statement from Lauricella to begin the meeting.
None of the school projects have optimized green building design and solar energy design opportunities used by many other Connecticut towns and cities for nearly a decade, Lauricella said. She asked that the projects be tabled to incorporate solar energy generation, including through solar panels over car ports, and to second opinions from other consultants.
Eric Gebrian of Consulting Engineering Services (CES) addressed those concerns, calling photovoltaics “much more viable” than geothermal heating and cooling because the photovoltaic prices are dropping rapidly. Geothermal systems would involve drilling 90 boreholes about 500 feet deep and would cost nearly $1 million more than photovoltaics and it would take about 58 years for the energy savings to counterbalance that expense.
Livingston pointed out that he hadn’t factored in possible energy cost changes, and Gebian said a 3 percent rate escalation would reduce the time to 40 years but CES considers a 20 year payback reasonable.
The company recommends a dedicated outdoor air system for HVAC. This would provide “100 percent fresh air directly to all the classrooms individually and then exhausting that air from each classroom out the building,” Gebian said. “So that’s a huge advantage for both indoor air quality and energy efficiency, especially with COVID happening now, I think is even more so a better solution.”
“It’s far more efficient than existing systems that you’ll see in schools that are, you know, 10-20-plus years old,” he said.
The classroom layout is streamlined, to provide flexibility as they can be repurposed, Lisa Yates said.
Council member David Heuvelman (D-District A) asked about disabilities act compliance; Yates said a freight elevator will be recontructed to allow space for stretchers and all the toilet room doorways will be expanded to be compliant.
In other business, the Committee unanimously voted to move the authorizations for Cranbury Elementary and the Naramake kitchen to the full Council for approval.
Leave a Reply
You must Register or Login to post a comment.